Translation Disclaimer

 The Environmental Impact Report is Certified!

On September 14, 2026, the City Council certified the programmatic EIR for the General Plan. The Certified EIR includes the Draft EIR and the Final EIR including Chapter 3 of the FEIR Errata (edits) to the DEIR, as well as the Mitigation Monitoring Program.

Final EIR

Chapter 1 Introduction

Chapter 2 Response to Comments

Chapter 3 Errata to the DEIR

Mitigation Monitoring and Reporting Program

Click here for the full FEIR.


Draft Environmental Impact Report 

Environmental resource topic areas covered in the DEIR are listed below with links to each chapter.

Table of Contents

Executive Summary

Chapters 1-4 (Introduction, Project Description, Environmental Setting, Environmental Analysis Intro)

4.1 Aesthetics

4.2 Agricultural & Forestry Resources

4.3 Air Quality

4.4 Biological Resources

4.5 Cultural Resources

4.6 Geology & Soils

4.7 Greenhouse Gas Emissions

4.8 Hazards & Hazardous Materials

4.9 Hydrology & Water Quality

4.10 Land Use & Planning

4.11 Noise

Appendices

Appendix A - B

Appendix C- G

Conclusions of the DEIR

CEQA provides a scale that rates the potential environmental impacts of implementing the General Plan. These ratings include:

  • No Impact: an indicator that the General Plan will have zero adverse effects

  • Less Than Significant Impact: an impact is minor and falls below the legal threshold

  • Less Than Significant Impact with Mitigation: an indicator that the impact could be potentially significant, but that with mitigation imposed that impact is reduced to a level below significance

  • Significant and Unavoidable: Despite the incorporation of proactive General Plan policies and feasible mitigation measures, the potentially significant impact cannot be reduced to a less-than-significant level with certainty and is therefore considered significant and unavoidable.

While the DEIR analyzes all the topics listed above and finds that draft General Plan policies and existing regulations keep most impacts at a "less than significant" level, it identifies certain SU impacts. For long-range city planning documents like a general plan, SU impacts are not uncommon and provide transparency about the trade-offs involved in community growth. An SU finding in a General Plan EIR acknowledges the inherent uncertainty associated with long term planning efforts.

While the programmatic DEIR identifies certain SU impacts, those findings should not be understood as predictions that such impacts will necessarily occur. Rather, they are disclosures required by CEQA at a programmatic level, based on conservative assumptions and without the benefit of project-specific information. Additional environmental analysis will be completed on a project-by-project basis to ensure that all feasible mitigation to lessen impacts will be implemented. Accordingly, impacts identified at this stage may ultimately be avoided or substantially reduced.

It is important to distinguish between the broad goals and policies established in the draft General Plan and the future site specific implementation of those policies. An SU finding acknowledges that while the draft General Plan sets a trajectory for growth, the ultimate extent of potential impacts and the effectiveness of mitigation cannot be fully known until a specific project is proposed and evaluated. It also acknowledges the difficulty and inherent uncertainty involved with forecasting future environmental conditions, particularly where future changes in technology, regulatory standards, and baseline conditions may occur.

Additional project-level environmental analysis will be required as specific developments are proposed and individual projects will undergo site-specific environmental review. Unlike the programmatic analysis in the DEIR, project level determinations are based on precise designs and site specific conditions. This increased level of detail often makes it possible to avoid or reduce impacts that were identified as SU at the program level.

The General Plan DEIR identifies the following areas as having Significant and Unavoidable Impacts:

Project Milestones

2025

Notice of Preparation (NOP). The NOP is an important milestone in the General Plan update process. It initiates the environmental review process and is intended to provide an opportunity for the public, as well as local and state agencies, to provide comments on the scope of the environmental analysis. This NOP public comment period began on August 8, 2025, and closed on September 8, 2025.

Scoping Meeting. The City held an in-person scoping meeting on August 21, 2025, at the Petaluma Community Center. The scoping meeting provided an opportunity for the public to learn about the environmental review process and provide verbal comments on the scope of the environmental review.

2026

Draft EIR. The DEIR was available for a 45-day public review period from March 27, 2026 to May 18, 2026.

Final EIR. The project team is preparing a Final EIR (FEIR), which will include written responses to comments received. The City Council held a public hearing and certified the EIR on September 14, 2026.